Guyana’s government has secured more time for the final disbursement of a US$527 million United States EXIM Bank loan for the Gas-to-Energy project, under amendments tabled in the National Assembly on Wednesday.
The government asked to move the deadline from September 1, 2026, to September 30, 2027, but the bank allowed an even later date of December 30, 2027. Kaieteur News reported that the financing changes come as the Wales project approaches another closely watched delivery deadline.
What the US EXIM Bank loan amendments say
US EXIM Bank approved the US$527 million loan to support a project initially priced at US$759 million. An agreement dated October 20, 2026, sets out why the disbursement schedule required amendment.
“By a letter dated as of September 29, 2026 (the ‘Waiver Request’) the borrower has requested that EXIM Bank amend and extend the final disbursement date within the credit agreement from September 1, 2026 to September 30, 2027,” the agreement states.
The bank approved the request and granted additional time to December 30, 2027, according to the agreement, “thus providing a somewhat longer extension than the borrower had requested in its waiver request.”
David Brooks, the bank’s acting senior vice president, signed for US EXIM. Senior Minister in the Office of the President with responsibility for Finance, Dr. Ashni Singh, signed for Guyana.
The amendment concerns the final loan disbursement, not a new public guarantee that the power plant will be completed by a particular date. That distinction matters because the project’s construction timetable has already shifted well beyond its original delivery target.
When will the 300MW Wales plant deliver power?
Lindsayca, the United States contractor, was initially expected to deliver both the 300-megawatt power plant and the Natural Gas Liquids facility by the end of 2024. The government’s recent statements instead point to initial generation by December 2026 and full capacity by mid-2027.
Minister of Public Utilities and Aviation Deodat Indar told an August media conference that he and the prime minister had received a commitment for one turbine supplying 57 megawatts to the national grid by the end of the year.
“At the end of the year, myself and the prime minister have gotten the commitment from Lindsayca, the Gas-to-Energy contractor that we will get one of the turbines that will generate 57MW of power,” Indar said.
Winston Brassington, head of the Gas-to-Energy task force, gave a broader timetable during this year’s energy conference. He said the contractor had promised to complete the plant’s simple-cycle phase by the end of 2026.
“Simple cycle is essentially the four gas turbines, with a total installed capacity of about 228 megawatts. So that we expect to have online by the end of the year,” Brassington said.
He added that the power plant’s combined-cycle stage and the Natural Gas Liquids plant were expected by the middle of 2027, bringing the installation to its full 300 megawatts.
The immediate test is therefore the arrival of the first 57 megawatts, followed by the four turbines supplying 228 megawatts. The remaining capacity will come from the steam-based combined-cycle stage.
Consumers must wait for the promised 50% reduction
The government has promised customers a 50% reduction in electricity bills once the first phase is complete. That relief will not begin until Lindsayca supplies at least 228 megawatts, meaning the single 57-megawatt turbine would not trigger it.
The prime minister clarified the threshold in response to a question from Kaieteur News.
“After the project, we said 50% reduction at the end of the project and the project we’re talking about is phase one. Phase one ends when we get 228 MW of power and then you got the 300MW that will come from the steam afterwards. So, when we achieve that, that’s phase one,” he said.
For households and businesses, the commissioning dates are consequently more important than the administrative extension of the loan. Cheaper electricity depends on generation reaching the grid at the required scale, not simply on financing remaining available.
Delays add to the public bill
The two-year delay has already forced Guyana to rent two power ships to help meet growing electricity demand. The Wales project is now expected to cost approximately US$884 million more than the initial cost of the two gas plants under construction, according to Kaieteur News.
That additional figure gives Parliament and the public a clear reason to scrutinise the amended financing arrangements alongside the construction schedule. The tabled agreement explains the new disbursement dates, but it does not provide a breakdown of the projected US$884 million increase.
Three dates now define the project’s public accountability: December 2026 for the first turbine and the 228-megawatt simple-cycle phase, mid-2027 for the full 300 megawatts, and December 30, 2027, for the final loan disbursement permitted by US EXIM Bank.
Until generation begins, consumers will continue waiting for the promised bill reduction while the country meets part of its electricity needs through rented generation.
Frequently asked questions
How long is the Gas-to-Energy loan extension?
Guyana requested a new final disbursement date of September 30, 2027. US EXIM Bank granted a longer extension, to December 30, 2027, replacing the original deadline of September 1, 2026.
When will electricity bills fall by 50%?
The government says the reduction will follow completion of phase one, when the project supplies 228 megawatts. The first 57-megawatt turbine alone will not meet that threshold.
How much extra is the delay expected to cost?
Kaieteur News reported that the two-year delay is expected to add approximately US$884 million to the initial cost of the two gas plants currently under construction.